  • What happenedNebius's ambitious 2027 buildout depends on customers prepaying for capacity that is not yet online, and the contracts underwriting that spending are already running past their original deployment dates.
  • Key facts & numbersNebius laid out $40 billion in planned spending for 2027 on its third-quarter earnings call, far more than Wall Street had expected; CFO Maria Del Dado Alonso Sanchez said customer prepayments plus asset-backed financing of investment-grade contracts are expected to cover up to 85% of its $40–45 billion capex. Microsoft's contract for capacity at Nebius's DataOne-operated Vineland, New Jersey site is worth up to $19.4 billion, but only just over half of that capacity is now planned for delivery by year-end, with the rest pushed to Q2 2027 — beyond the 2025–2026 window the tranches were meant for. The contract lets Microsoft terminate affected service after a grace period if dates are missed and no alternative capacity is offered, and carries financial penalties for late delivery; Nebius did not say whether Microsoft has agreed to the new dates, and Microsoft has not publicly canceled anything. DataOne said it "decided to wind down the temporary generation faster than it was expected" as the Vineland site switches over to Bloom Energy fuel cells. Floodlight identified at least 45 natural gas generators operating at the site without permits, New Jersey regulators fined the facility $1.1 million for violating federal law, and the operator faces a noise-complaint lawsuit from nearby residents.
  • What happens nextA third of Nebius's 571% revenue jump was a one-time payment — and the $19.4B Microsoft contract carries termination rights.
  • Nebius laid out $40 billion in planned spending for 2027 on its third-quarter earnings call, far more than Wall Street had expected; CFO Maria Del Dado Alonso Sanchez said customer prepayments plus asset-backed financing of investment-grade contracts are expected to cover up to 85% of its $40–45 billion capex.
  • Microsoft's contract for capacity at Nebius's DataOne-operated Vineland, New Jersey site is worth up to $19.4 billion, but only just over half of that capacity is now planned for delivery by year-end, with the rest pushed to Q2 2027 — beyond the 2025–2026 window the tranches were meant for. The contract lets Microsoft terminate affected service after a grace period if dates are missed and no alternative capacity is offered, and carries financial penalties for late delivery; Nebius did not say whether Microsoft has agreed to the new dates, and Microsoft has not publicly canceled anything.
  • DataOne said it "decided to wind down the temporary generation faster than it was expected" as the Vineland site switches over to Bloom Energy fuel cells. Floodlight identified at least 45 natural gas generators operating at the site without permits, New Jersey regulators fined the facility $1.1 million for violating federal law, and the operator faces a noise-complaint lawsuit from nearby residents.
  • Nebius said the delays are confined to sites it does not control, that its own data centers are coming online on time or ahead of schedule and will supply most of its new capacity from 2027, and that new Q3 deals came with prepayments more than covering the cost of building the capacity behind them, CRO Marc Boroditsky said. CEO Arkady Volozh added: "Building at this scale is hard, and delays are part of our industry right now. We are not immune."

Why It Matters

Nebius is financing a $40 billion buildout with customer contracts that are already late: Microsoft's deal covers up to $19.4 billion of capacity, allows termination after a grace period, and now runs to Q2 2027. Microsoft's own capex is running below plan on third-party delays, and Nebius shares ended the day down 17%.