An Unused and Divisive Philippine Nuclear Plant Awaits Its Fate

The 30-Second Skim7 points
- What happenedThe Philippines is weighing whether to restart the Bataan Nuclear Power Plant, completed in 1984 but never turned on, as part of a broader push to bolster energy security against global shocks.
- Key facts & numbersFerdinand Marcos Jr., elected president in 2022, has revived the Philippines' pursuit of atomic energy and is exploring options including potentially restarting the Bataan Nuclear Power Plant, mothballed for roughly 40 years. The Bataan Nuclear Power Plant sits on an 800-acre compound near the seaside town of Morong, west of Manila, where manager Noel Germano and seven engineers manually turn thousands of analog dials, switches, and gears to prevent decay. The plant's lone completed reactor was finished in 1984 under President Ferdinand Marcos Sr. — one of four originally planned units — and was designed to produce 621 megawatts but was never switched on.
- What happens nextForty years, one completed reactor, zero electrons produced. The Marcos dynasty bookends this one — dad built it, son might finally flip the switch.
- Ferdinand Marcos Jr., elected president in 2022, has revived the Philippines' pursuit of atomic energy and is exploring options including potentially restarting the Bataan Nuclear Power Plant, mothballed for roughly 40 years.
- The Bataan Nuclear Power Plant sits on an 800-acre compound near the seaside town of Morong, west of Manila, where manager Noel Germano and seven engineers manually turn thousands of analog dials, switches, and gears to prevent decay.
- The plant's lone completed reactor was finished in 1984 under President Ferdinand Marcos Sr. — one of four originally planned units — and was designed to produce 621 megawatts but was never switched on.
- Experts say restarting the plant is "not impossible, but a tall and expensive ask," given decades of dormancy and the analog technology involved.
Why It Matters
The Philippines would inherit a 621-megawatt reactor that has sat idle since 1984 — a potential energy-security win against global shocks, but only after what experts call a tall and expensive technical overhaul. A revival decision would force the Marcos Jr. administration to weigh decades-old analog infrastructure and an 800-acre Morong site against the cost and complexity of a restart.