- What happened: Google's $15bn AI datacentre project in Tarluvada, Andhra Pradesh, is facing mounting opposition from villagers and activists who allege land was confiscated without notice, environmental clearances were rubber-stamped in nine days, and the true scale of the facility was obscured from the public.
- Key facts & numbers: Google is building a $15bn AI datacentre in Tarluvada, Andhra Pradesh, in partnership with the Adani Group — its largest hyperscale AI facility outside the US, encompassing three sites around Vizakhapatnam State environmental clearances issued in just nine days reveal the project is approved at 2.51GW capacity, more than double the publicly announced 1GW and equivalent to two large nuclear reactors running at full output India's National Green Tribunal has received three petitions alleging the state's environmental assessment was 'grossly inadequate, scientifically unrealistic, and misleading,' alongside a separate public-interest litigation in the Andhra Pradesh high court
- What happens next: Nine days for environmental clearance on a 2.51GW nuclear-reactor-equivalent. Villagers' land fenced off by Adani guards with no warning.
- Google is building a $15bn AI datacentre in Tarluvada, Andhra Pradesh, in partnership with the Adani Group — its largest hyperscale AI facility outside the US, encompassing three sites around Vizakhapatnam
- State environmental clearances issued in just nine days reveal the project is approved at 2.51GW capacity, more than double the publicly announced 1GW and equivalent to two large nuclear reactors running at full output
- India's National Green Tribunal has received three petitions alleging the state's environmental assessment was 'grossly inadequate, scientifically unrealistic, and misleading,' alongside a separate public-interest litigation in the Andhra Pradesh high court
- 520 families in Tarluvada had land confiscated; 47 Dalit farmers say promised replacement plots and one job per family never materialised after receiving $40,000 each in compensation
Why It Matters
Andhra Pradesh cleared Google's datacentre in nine days at a publicly announced 1GW, though approvals actually cover 2.51GW — equal to two nuclear reactors and 30% of state electricity consumption. Three NGT petitions and a high court suit now challenge that approval, while 520 families allege their land was fenced off without notice for a project subsidized with $2.2bn in state incentives.