Croatia tenders 56 MW solar project with 200 MWh storage

The 30-Second Skim7 points

  • What happenedCroatia's state-owned power company HEP has launched a two-stage tender for a developer to build a 56 MW solar plant paired with up to 200 MWh of battery storage in Zadar county, with pre-qualification bids due May 12.
  • Key facts & numbersHrvatska Elektroprivreda (HEP) launched an open two-stage tender for a developer to build a 56 MW solar plant alongside up to 200 MWh of battery energy storage in Sukošan municipality, Zadar county, with pre-qualification proposals due May 12. The project is backed by the European Bank for Reconstruction and Development (EBRD), which is hosting the tender listing, and includes construction of a new 100/33 kV substation connected to the existing 110 kV Zadar–Istok Biograd transmission line. HEP has already obtained a location permit for the 54.8-hectare site, expects a construction permit by Q2 2027, and is targeting the ready-to-build stage by the end of 2026.
  • What happens nextCroatia just crossed 1.2 GW of solar and is about to pass wind — this 56 MW / 200 MWh HEP hybrid is the storage-paired build the grid actually needs.
  • Hrvatska Elektroprivreda (HEP) launched an open two-stage tender for a developer to build a 56 MW solar plant alongside up to 200 MWh of battery energy storage in Sukošan municipality, Zadar county, with pre-qualification proposals due May 12.
  • The project is backed by the European Bank for Reconstruction and Development (EBRD), which is hosting the tender listing, and includes construction of a new 100/33 kV substation connected to the existing 110 kV Zadar–Istok Biograd transmission line.
  • HEP has already obtained a location permit for the 54.8-hectare site, expects a construction permit by Q2 2027, and is targeting the ready-to-build stage by the end of 2026.
  • Croatia's cumulative solar capacity passed 1.2 GW by the start of December 2025, and solar is forecast to surpass wind in installed capacity for the first time in 2026.

Why It Matters

HEP's project pairs 200 MWh of battery storage with 56 MW of solar — roughly 3.6 hours of full-output duration — making it one of Croatia's larger hybrid utility-scale builds. It advances a national solar fleet that crossed 1.2 GW in December 2025, on track to overtake wind in installed capacity this year.