Energy Dome, Salt River Project to build 19-MW CO2 battery system

The 30-Second Skim
- What happened: Energy Dome and Salt River Project announced a 20-year tolling agreement to install a 19-MW carbon dioxide battery system at a coal-to-gas conversion site in Arizona, with Google funding a portion through a cost-sharing deal.
- Key facts & numbers: Energy Dome and Salt River Project announced a 20-year tolling agreement to build a 19-MW, 10-hour CO2 battery system co-located at SRP's Coronado Generating Station in St. Johns, Arizona, expected to come online in 2029. The system will store enough energy to power approximately 4,275 homes for 10 hours, using Energy Dome's proprietary thermomechanical process that compresses CO2 for storage and expands it through a turbine to generate electricity. Google, which made a 'strategic investment' in Milan-based Energy Dome last year, will fund a portion of the project through a cost-sharing agreement with SRP and said the technology 'has the potential to commercialize much faster than some of the other advanced clean energy technologies in our portfolio.'
- What happens next: Google's betting on CO2 batteries for its data centers while the host site literally transitions off coal. Long-duration storage finally has a real deadline.
- Energy Dome and Salt River Project announced a 20-year tolling agreement to build a 19-MW, 10-hour CO2 battery system co-located at SRP's Coronado Generating Station in St. Johns, Arizona, expected to come online in 2029.
- The system will store enough energy to power approximately 4,275 homes for 10 hours, using Energy Dome's proprietary thermomechanical process that compresses CO2 for storage and expands it through a turbine to generate electricity.
- Google, which made a 'strategic investment' in Milan-based Energy Dome last year, will fund a portion of the project through a cost-sharing agreement with SRP and said the technology 'has the potential to commercialize much faster than some of the other advanced clean energy technologies in our portfolio.'
- The battery will sit at Coronado Generating Station, which is converting from coal to natural gas — natural gas conversion due by 2029, with all coal generation ceasing by 2032.
Why It Matters
SRP gets a real-world test of CO2 battery technology at a coal-to-gas conversion site as it races to double generating capacity by 2035 for Phoenix-area demand. Google locks in a near-term clean energy tool it explicitly plans to pair with data center demand response, betting that CO2 storage commercializes faster than other advanced technologies in its portfolio.