FERC approves MISO plan to speed legacy interconnection study process

The 30-Second Skim
- What happened: FERC approved MISO's plan to clear its backlog of power project interconnections by allowing penalty-free withdrawals and limiting restudies, aiming to speed up grid access for nearly 125 GW of queued projects.
- Key facts & numbers: FERC approved MISO’s tariff revisions on October 19 to accelerate the legacy interconnection study process for the Definitive Planning Phase–2022 queue, which contains about 35 GW of active projects. MISO implemented a penalty-free exit option before Decision Point II (October 20) to reduce delays caused by late project withdrawals that trigger costly restudies in its 600-project, 125 GW interconnection queue. MISO limited restudies to one per project in Definitive Planning Phase III for the 2022 cycle and all future cycles, addressing cascading delays from repeated network upgrade reassessments.
- What happens next: FERC greenlights MISO’s queue cleanup—penalty-free exits return, but only if costs jump 50%. The real win? One restudy max, ending endless delays.
- FERC approved MISO’s tariff revisions on October 19 to accelerate the legacy interconnection study process for the Definitive Planning Phase–2022 queue, which contains about 35 GW of active projects.
- MISO implemented a penalty-free exit option before Decision Point II (October 20) to reduce delays caused by late project withdrawals that trigger costly restudies in its 600-project, 125 GW interconnection queue.
- MISO limited restudies to one per project in Definitive Planning Phase III for the 2022 cycle and all future cycles, addressing cascading delays from repeated network upgrade reassessments.
- FERC upheld a 50% network upgrade cost increase threshold for penalty-free withdrawal, rejecting Pathway Power’s argument that MISO failed to justify the higher bar compared to the previous 35% standard.
Why It Matters
Grid developers now face a higher bar to exit without penalty, but gain faster processing for viable projects. The change prevents restudy bottlenecks that delayed 35 GW of clean energy, directly affecting timelines for solar, wind, and battery projects worth billions in investment.