FirstEnergy utilities get approval for $2.5B gas plant in West Virginia

The 30-Second Skim3 points
- What happenedThe PSC approved Mon Power and Potomac Edison’s plan for a 1.2-GW combined-cycle gas plant and 70 MW of solar. Residential customers are initially expected to see a $1.18 monthly surcharge, or 0.9%, as construction costs are recovered.
- Key facts & numbersThe Maidsville Energy Center is expected to cost $2.48 billion and enter service in late 2031; the broader plan adds 70 MW of solar. Residential bills are initially expected to rise $1.18 per month, or 0.9%.
- What happens nextThe surcharge is recalculated every six months using actual construction-work-in-progress balances. After a late-2031 gas-plant launch, assets would enter base rates; a construction stop or extraordinary delays would trigger a new PSC proceeding.
Why It Matters
PSC analysis ties the build to a 100 MW need in 2028, a projected 60 MW shortfall and a 2,194 MW gap by 2034, amid surging PJM Interconnection capacity prices.
The financing tradeoff is explicit: residential customers would pay a surcharge during construction, while Sierra Club says customers prompting the upgrades should bear more cost through large-load tariffs. The commission also cited more than $80 million recovered for Pepco Holdings’ canceled project; a stop or extraordinary delay would require a new proceeding to determine treatment and timing.
How Outlets Are Framing It
Observations from the coverage. No single outlet is named.
- The headline and article body converge on PSC approval, making the $2.48 billion Maidsville gas plant the central outcome while the 70 MW solar component stays secondary.
- The decision’s less visible consequence is construction-cost recovery through a monthly surcharge—initially $1.18, or 0.9%—before the assets enter base rates following the plant’s launch.
- Staff’s 100-to-1,012 MW forecast supports the build, while intervenors question whether data-center growth will materialize and criticize shifting project costs to ratepayers through the surcharge.
Background & Timeline
- 2026: Commission analysis projected Mon Power’s summer peak at 2,997 MW and a possible 60 MW shortfall in 2028 as new large loads were added.
- Before Nov. 17: A prior construction surcharge for Pepco Holdings’ canceled Mid Atlantic Power Pathway ultimately produced more than $80 million in ratepayer recovery.
Sources Cited
- Charleston Gazette-MailFirstEnergy planning to spend $2.5B as it seeks 1.2GW of new gas-fired power in WV