Meta Quits RE100, Funds 10 Gas Plants for AI Data Centers

The 30-Second Skim7 points
- What happenedMeta has abandoned its RE100 commitment to 100% renewable electricity and is now backing a fleet of 10 gas-fired power plants totaling roughly 7.5 GW to fuel AI data center expansion in Louisiana.
- Key facts & numbersMeta quit RE100, the global corporate initiative whose members pledge 100% renewable electricity, a split first reported by Recharge on July 23; Meta had joined in 2016 as Facebook and claimed in 2021 to have hit its target using renewable energy certificates (RECs) and power purchase agreements (PPAs). At its Hyperion data center in Richland Parish, Louisiana, Meta is now funding 10 combined-cycle gas plants totaling roughly 7.5 GW — an original three-plant, ~2.26 GW buildout expanded by a March 2026 Entergy Louisiana deal adding seven more plants exceeding 5.2 GW. Meta is also tied to a 200 MW behind-the-meter gas project in Ohio announced in June 2025, and says gas is 'necessary' where utilities cannot meet its AI power needs while seeking certificates for lower-methane gas.
- What happens next'100% renewable' = '100% offset on paper,' and Meta is building 10 gas plants anyway. The pledge lasted exactly as long as AI got hungry.
- Meta quit RE100, the global corporate initiative whose members pledge 100% renewable electricity, a split first reported by Recharge on July 23; Meta had joined in 2016 as Facebook and claimed in 2021 to have hit its target using renewable energy certificates (RECs) and power purchase agreements (PPAs).
- At its Hyperion data center in Richland Parish, Louisiana, Meta is now funding 10 combined-cycle gas plants totaling roughly 7.5 GW — an original three-plant, ~2.26 GW buildout expanded by a March 2026 Entergy Louisiana deal adding seven more plants exceeding 5.2 GW.
- Meta is also tied to a 200 MW behind-the-meter gas project in Ohio announced in June 2025, and says gas is 'necessary' where utilities cannot meet its AI power needs while seeking certificates for lower-methane gas.
- Rivals Apple, Google, and Microsoft remain on RE100's 444-company roster, though Google agreed to buy power from a 400 MW Illinois gas plant with carbon capture and Microsoft signed a 20-year deal for a 2.67 GW gas plant at its West Texas data center.
Why It Matters
Meta's exit from RE100 turns '100% renewable' into an annual accounting match that leaves gas plants running around the clock to serve AI data centers — a path Apple, Google, and Microsoft have so far declined to take while remaining on the 444-company pledge, leaving Meta to absorb the reputational risk alone.
Sources Cited
- E&E News by POLITICOMeta plans 7 new gas plants to power massive Louisiana data center