PJM Fast-Tracks 2.1 GW from Engie, LS Power

The 30-Second Skim
- What happened: PJM Interconnection approved 2.1 GW of new capacity through its new Expedited Interconnection Track — an 860-MW and 800-MW battery storage project from Engie plus a 455-MW gas uprate from LS Power — with all three targeted for mid-2029.
- Key facts & numbers: PJM Interconnection approved three projects totaling 2.1 GW in its new Expedited Interconnection Track process, targeting commercial operation by mid-2029. Engie IR Holdings won approval for two battery storage facilities: an 860-MW project in Crawford, Pennsylvania, and an 800-MW project in Morrow, Ohio. LS Power received approval to add 455 MW to its 810-MW combined cycle Hunterstown power plant in Adams, Pennsylvania — a gas-fired facility the company acquired from Platinum Equity in 2024.
- What happens next: Two batteries and a gas uprate — that's what "expedited" looks like when supply is tight and data centers are eating the queue.
- PJM Interconnection approved three projects totaling 2.1 GW in its new Expedited Interconnection Track process, targeting commercial operation by mid-2029.
- Engie IR Holdings won approval for two battery storage facilities: an 860-MW project in Crawford, Pennsylvania, and an 800-MW project in Morrow, Ohio.
- LS Power received approval to add 455 MW to its 810-MW combined cycle Hunterstown power plant in Adams, Pennsylvania — a gas-fired facility the company acquired from Platinum Equity in 2024.
- FERC approved the Expedited Interconnection Track process in June; PJM opened the application window on July 31 for projects above 250 MW backed by a primary siting authority and capable of operating within three years.
Why It Matters
PJM is using the Expedited track to pull 2.1 GW of new capacity onto a grid that has seen little new generation built in recent years while data-center demand pushes forecasts higher and capacity costs have spiked — delivering a concrete storage-plus-gas mix (860 MW and 800 MW of batteries from Engie, plus a 455-MW gas uprate from LS Power) before the process sunsets at the end of 2027.