PJM eyes hybrid fix to jumpstart surplus interconnection

The 30-Second Skim
- What happened: PJM Interconnection is exploring new rule changes to make its Surplus Interconnection Service pathway functional, after its early-2025 reforms yielded just two approvals out of eight applications since 2023 and the grid operator fell short on its last two capacity auction reserve margins.
- Key facts & numbers: PJM Interconnection floated an "issue charge" allowing hybrid resources to participate in energy and ancillary services markets as separate, independent resources — a fix stakeholders say is needed because the current single-ID model prevents co-located batteries from accessing capacity interconnection rights tied to an existing generator. MISO had 44 surplus interconnection projects online and SPP had 22, compared with PJM's approval of just 2 of 8 applications since 2023, per a late November presentation and an analysis by advisory firm Surplus Interconnection. PJM missed reserve margin targets in its last two capacity auctions, with the shortfall growing to 6.8 GW for the 2028/29 delivery year from 6.5 GW for 2027/28, intensifying pressure to find faster pathways for new capacity.
- What happens next: MISO and SPP have 44 and 22 operational surplus projects; PJM has approved 2 of 8. A 6.8 GW capacity shortfall is forcing the fix.
- PJM Interconnection floated an "issue charge" allowing hybrid resources to participate in energy and ancillary services markets as separate, independent resources — a fix stakeholders say is needed because the current single-ID model prevents co-located batteries from accessing capacity interconnection rights tied to an existing generator.
- MISO had 44 surplus interconnection projects online and SPP had 22, compared with PJM's approval of just 2 of 8 applications since 2023, per a late November presentation and an analysis by advisory firm Surplus Interconnection.
- PJM missed reserve margin targets in its last two capacity auctions, with the shortfall growing to 6.8 GW for the 2028/29 delivery year from 6.5 GW for 2027/28, intensifying pressure to find faster pathways for new capacity.
- MN8 Energy senior manager Grant Glazer said many PJM solar projects have interconnection rights covering only 40%–60% of nameplate capacity, leaving substantial spare capacity that surplus interconnection could monetize.
Why It Matters
For PJM to close a 6.8 GW capacity shortfall without costly network upgrades, it must unlock tens of thousands of megawatts of unused interconnection rights at existing generators — but the current hybrid-resource market structure blocks co-located batteries from accessing those rights. If PJM's proposed rule change clears its Market Implementation Committee, developers like MN8 Energy can fast-track battery projects by attaching them to solar farms' spare CIRs, sidestepping the multi-year standard interconnection queue.