Tenaska options 2,600 acres for Google AI data center
The 30-Second Skim7 points
- What happenedTenaska has optioned over 2,600 acres in southeast Nebraska for documents suggesting a Google-operated AI data center powered by a 1,000-3,000 MW gas plant with carbon capture, while a state senator who signed a land deal hasn't disclosed the potential conflict.
- Key facts & numbersTenaska has entered into agreements with landowners for over 2,600 acres across southeast Nebraska since December under two LLC names, securing exclusive options to buy the land for a project documents link to a Google data center and utility-scale natural gas plant. Documents shared at a January Nebraska public power district meeting name Google, Tenaska, and Tallgrass Energy, projecting 1,000-3,000 megawatts of power demand — potentially more than the largest power plant currently in the state — with the facility possibly online as soon as 2029. If the project incorporates carbon capture and storage as outlined, it would be the largest such operation in the United States, according to Yale economist Kenneth Gillingham — though Tallgrass, named in the documents as the would-be carbon transporter, publicly denies any partnership.
- What happens nextSenator signed a Tenaska land deal, didn't disclose it, and his chamber debates the bill enabling the project. Rep told a farmer 'business park' — then slipped and said AI.
- Tenaska has entered into agreements with landowners for over 2,600 acres across southeast Nebraska since December under two LLC names, securing exclusive options to buy the land for a project documents link to a Google data center and utility-scale natural gas plant.
- Documents shared at a January Nebraska public power district meeting name Google, Tenaska, and Tallgrass Energy, projecting 1,000-3,000 megawatts of power demand — potentially more than the largest power plant currently in the state — with the facility possibly online as soon as 2029.
- If the project incorporates carbon capture and storage as outlined, it would be the largest such operation in the United States, according to Yale economist Kenneth Gillingham — though Tallgrass, named in the documents as the would-be carbon transporter, publicly denies any partnership.
- Governor Jim Pillen has proposed LB1261, which would let private power plants serving large industrial facilities hook into the public grid and sell excess power back; Tenaska has publicly backed the bill, and reporter Zoeller says the governor's office consulted with the companies tied to this proposal before drafting it.
Why It Matters
Senator Dorn's undisclosed Tenaska land option, signed while his chamber debates the bill that unlocks the project, is a textbook conflict-of-interest problem. Nebraska ratepayers could end up paying for grid connections to a private gas plant serving a single corporate customer, and if the carbon capture piece doesn't work, the state is left with one of its largest-ever emitters.
Sources Cited
- Studio InternationalA look behind the scenes of the travelling exhibition on Berthe Weill
- ShareAmerica (.gov)Behind the scenes: A look back at the Cuban missile crisis
Related Coverage
The day’s news in one short email, every morning.