Offshore Wind Farms Defy Trump's Stop-Work Orders

The 30-Second Skim
- What happened: Vineyard Wind installed all 62 turbines by March 13, and Revolution Wind began delivering power the same day, marking major milestones for the U.S. offshore wind industry despite repeated Trump administration stop-work orders.
- Key facts & numbers: Vineyard Wind installed all 62 turbines by March 13 — down from 84 in the original 2017 proposal — with full commissioning to follow, after a federal court lifted BOEM's December 22 stop-work order in late January. Revolution Wind began delivering electricity to the grid for the first time on March 13, a 704-MW joint venture between Ørsted and Skyborn Renewables expected to save New England ratepayers up to $500 million annually per a September 2024 Connecticut DEEP report. BOEM's December 22 stop-work order targeted five Atlantic Coast wind farms citing unspecified national security concerns, yet on the same day the agency quietly allowed Vineyard Wind to keep its 44 already-commissioned turbines operating.
- What happens next: Every time BOEM tried to stop these wind farms, the courts slapped them down — and now five are nearly done. The nightmare is fossil fuels'.
- Vineyard Wind installed all 62 turbines by March 13 — down from 84 in the original 2017 proposal — with full commissioning to follow, after a federal court lifted BOEM's December 22 stop-work order in late January.
- Revolution Wind began delivering electricity to the grid for the first time on March 13, a 704-MW joint venture between Ørsted and Skyborn Renewables expected to save New England ratepayers up to $500 million annually per a September 2024 Connecticut DEEP report.
- BOEM's December 22 stop-work order targeted five Atlantic Coast wind farms citing unspecified national security concerns, yet on the same day the agency quietly allowed Vineyard Wind to keep its 44 already-commissioned turbines operating.
- Empire Wind in New York was first halted in April 2025 despite being greenlit during Trump's first term, restarted after Governor Kathy Hochul personally negotiated with Trump in May 2025, then halted again in December before winning court relief earlier this year.
Why It Matters
New England ratepayers stand to save up to $500 million annually in wholesale energy costs from Revolution Wind alone, while federal courts have now repeatedly overturned Trump's stop-work orders — meaning projects already under construction keep delivering power regardless of executive action.