Exelon, Invenergy Seek FERC Capacity Market Reforms

The 30-Second Skim
- What happened: Exelon and Invenergy Transmission filed separate complaints at FERC seeking reforms to capacity markets in PJM and MISO, citing outdated auction timing and unfair exclusion of merchant transmission lines from compensation.
- Key facts & numbers: Exelon asked FERC to order PJM to adopt a 'prompt' capacity auction starting in 2030, shifting from the current three-year-forward model to one held two months before the delivery year begins. Exelon argued the proposed auction shift would improve market signals and resource entry/exit efficiency by relying on more accurate load and availability data closer to the delivery period. PJM is reviewing Exelon’s complaint and has invited stakeholder proposals on capacity market reform, with over 30 responses received and a workshop scheduled for Nov. 13.
- What happens next: Two big players, two different grid market gripes: Exelon wants auctions closer to delivery, Invenergy wants paid for delivering capacity MISO already counts.
- Exelon asked FERC to order PJM to adopt a 'prompt' capacity auction starting in 2030, shifting from the current three-year-forward model to one held two months before the delivery year begins.
- Exelon argued the proposed auction shift would improve market signals and resource entry/exit efficiency by relying on more accurate load and availability data closer to the delivery period.
- PJM is reviewing Exelon’s complaint and has invited stakeholder proposals on capacity market reform, with over 30 responses received and a workshop scheduled for Nov. 13.
- Invenergy Transmission filed a complaint alleging MISO uses HVDC transmission lines to reduce needed capacity purchases but denies those lines compensation for their accredited capacity value.
Why It Matters
Exelon’s push could delay PJM’s 2030/31 auction and force a structural overhaul of a market underpinning power reliability for 10.7 million customers, while Invenergy’s complaint challenges a key barrier to private transmission investment in MISO, where lines contribute value but receive no pay.