- What happened: Utility executives see no slowdown in power-demand growth, and Goldman Sachs expects election-era data-center moratoria to spare most planned 2027 construction as EVs, reshoring and electrification sustain load for now.
- Key facts & numbers: Edison Electric Institute conference attendees including Exelon executive Calvin Butler, Entergy executive Drew Marsh and EEI head Drew Maloney all said their internal electricity-growth estimates showed no slowdown; EVs, reshoring and electrification also add to demand. Goldman Sachs expects moratoria by newly elected governors in states accounting for over one-third of planned U.S. data-center capacity to affect mostly projects not yet permitted, leaving most planned 2027 construction unaffected; it still estimates roughly $1.4 trillion in AI-hardware spending by the end of next year. Texas Gov. Greg Abbott has paused data-center permitting; PUCT's Thomas Gleeson and TCEQ's Brooke Paup serve through September 2029 and next year, respectively, although the author cautions that other state powers could still alter the outcome.
- What happens next: Broader than two stocks: EVs, reshoring and electrification—not data centers alone—kept utility CEOs' growth outlooks intact.
- Edison Electric Institute conference attendees including Exelon executive Calvin Butler, Entergy executive Drew Marsh and EEI head Drew Maloney all said their internal electricity-growth estimates showed no slowdown; EVs, reshoring and electrification also add to demand.
- Goldman Sachs expects moratoria by newly elected governors in states accounting for over one-third of planned U.S. data-center capacity to affect mostly projects not yet permitted, leaving most planned 2027 construction unaffected; it still estimates roughly $1.4 trillion in AI-hardware spending by the end of next year.
- Texas Gov. Greg Abbott has paused data-center permitting; PUCT's Thomas Gleeson and TCEQ's Brooke Paup serve through September 2029 and next year, respectively, although the author cautions that other state powers could still alter the outcome.
- Louisiana: Sources said projects not built in Texas would go to Louisiana, Oklahoma or another state, and Gov. Jeff Landry's team is already calling companies; both Louisiana and Oklahoma are gas-rich, have ample power and want the investment.
Why It Matters
Utility investors get more than the data-center thesis: every utility CEO interviewed reported no slowdown, with EVs, reshoring and electrification adding to load. Goldman Sachs' $1.4 trillion hardware-spending estimate by end of next year supports infrastructure demand, while First Solar's 22% decline since Deutsche Bank's early-July upgrade shows why an endorsement alone does not guarantee a stock gain.