Digital Realty falls 5% after taking $3.5 billion stake in Blackstone's Virginia data centers

Image from CNBC

The 30-Second Skim7 points

  • What happenedDigital Realty's stock dropped about 5.4% in premarket trading after the Austin-based data center firm announced a $3.5 billion deal to acquire Blackstone's stake in three Northern Virginia data centers valued at $7.8 billion.
  • Key facts & numbersDigital Realty fell roughly 5.4% in premarket trading Monday on news it will pay $3.5 billion ($1.2B cash plus $2.3B in shares) for Blackstone's 80% interest in two 96MW Manassas data centers and 50% interest in one 96MW Sterling data center, with the portfolio valued at $7.8B. Greg Wright, Digital Realty's chief investment officer, called the transaction the next phase of its Blackstone partnership and a way to deepen ownership of "fully leased, high-quality hyperscale assets." The two Manassas facilities are slated to stabilize in H1 2027, with the Sterling facility following in H1 2028; the deal is expected to close Tuesday.
  • What happens nextMarket hated the stock-and-cash structure more than the asset: $3.5B for stakes in data centers virtually everyone else is scrambling to lease too.
  • Digital Realty fell roughly 5.4% in premarket trading Monday on news it will pay $3.5 billion ($1.2B cash plus $2.3B in shares) for Blackstone's 80% interest in two 96MW Manassas data centers and 50% interest in one 96MW Sterling data center, with the portfolio valued at $7.8B.
  • Greg Wright, Digital Realty's chief investment officer, called the transaction the next phase of its Blackstone partnership and a way to deepen ownership of "fully leased, high-quality hyperscale assets."
  • The two Manassas facilities are slated to stabilize in H1 2027, with the Sterling facility following in H1 2028; the deal is expected to close Tuesday.
  • Despite Monday's premarket slide, Digital Realty shares remain up 23% year-to-date.

Why It Matters

Digital Realty is paying a premium in stock to consolidate control of fully leased Virginia hyperscale capacity just as the market shows near-zero vacancy risk through 2030, and peers like Amazon, Microsoft, Meta, and Google are channeling an estimated $700 billion in 2025 capex into the same constrained geography — meaning incumbents with prime Virginia land now hold the scarce input.