Google’s power-hungry data centers crave nuclear energy

The 30-Second Skim
- What happened: Google signed a 20-year deal with Constellation to fund $4.3 billion in upgrades at six U.S. nuclear plants, adding 890 megawatts of capacity to feed its rapidly expanding data center footprint.
- Key facts & numbers: Google signed a 20-year power purchase agreement with Constellation covering efficiency upgrades at 11 reactors across 6 sites in Illinois, Pennsylvania, and New Jersey, representing more than $4.3 billion in new investment by Constellation Constellation will modernize the reactors over the next five years to add 890 megawatts of nuclear capacity — roughly equivalent to one large reactor or three small modular reactors PJM Interconnection, the largest U.S. power grid spanning 13 states and D.C., has struggled to meet AI data center demand; an independent monitor warned FERC last year that PJM was approving connections it couldn't reliably serve, risking blackouts
- What happens next: FERC forced PJM to postpone its own power auction because data centers might spike everyone else's bills. The nuclear PR push can't mask that math.
- Google signed a 20-year power purchase agreement with Constellation covering efficiency upgrades at 11 reactors across 6 sites in Illinois, Pennsylvania, and New Jersey, representing more than $4.3 billion in new investment by Constellation
- Constellation will modernize the reactors over the next five years to add 890 megawatts of nuclear capacity — roughly equivalent to one large reactor or three small modular reactors
- PJM Interconnection, the largest U.S. power grid spanning 13 states and D.C., has struggled to meet AI data center demand; an independent monitor warned FERC last year that PJM was approving connections it couldn't reliably serve, risking blackouts
- PJM postponed its power auction last week after FERC directed revisions to prevent data centers from raising electricity bills for other customers — New Jersey rates have climbed 54% over five years
Why It Matters
Google just locked in 890 MW of new nuclear capacity plus a separate 2,700 MW energy deal, betting on baseload power to feed its data center buildout. But PJM is already straining — New Jersey rates climbed 54% in five years — and FERC just forced PJM to postpone its own power auction to keep data centers from pushing bills higher for everyone else.