- CMS Energy CEO Garrick Rochow told investors the Microsoft-linked data center project is progressing through zoning in multiple locations, despite a permitting setback in April.
- Consumers Energy did not include its multi-gigawatt large-load pipeline slide in its Q3 earnings presentation, a move Rochow said was intentional to focus on execution over planning.
- CMS Energy reported $0.39 per share earnings for Q3 2026, down from $0.92 per share in the same quarter of 2025, citing asset impairments tied to NorthStar Clean Energy.
- NorthStar Clean Energy has had over 35% of its assets sold or agreed to be sold, with most of the remainder in advanced negotiations as CMS works to complete restructuring by year-end.
- CMS Energy expects to reallocate at least $500 million from NorthStar to its utility business, with CFO Sri Maddipati suggesting the final benefit could exceed that estimate.
- Consumers Energy has energized 450 MW of new large load under its five-year plan, excluding the Microsoft data center, which could add up to 1 GW and drive $2B–$5B in utility investment.
Why it matters: The Microsoft-linked data center’s progress hinges on post-midterm local permitting, and CMS’s decision to withhold its large-load slide signals heightened sensitivity to political optics. With $500M+ in capital redirected to utilities and 1 GW of potential load at stake, the outcome affects rate base growth, regulatory scrutiny, and clean energy investment pacing in Michigan.