Nvidia Halves $250B OpenAI Data Center Backstop

SkimNews Take
Nvidia halving its initial guarantee signals staged-exposure financing: the restructured terms shift the burden of funding the remaining $125B onto other lenders while capping Nvidia's upfront risk.
Get the Tech newsletter
Daily tech — startups, AI labs, chips, the launches that shape the next decade. Free.
- Nvidia has reworked a deal to finance an OpenAI data center campus in Ohio, with the project totaling 10 gigawatts of capacity
- Under the new proposed terms, Nvidia would initially guarantee only half of its planned $250 billion backstop for the Ohio campus
Why it matters: The restructuring trims Nvidia's near-term exposure on the 10-gigawatt Ohio campus, with the chip maker initially backstopping roughly $125 billion instead of the full $250 billion. The reduced initial commitment lets Nvidia preserve the broader OpenAI partnership while staging its financial risk as the project ramps up.
Ask SkimNews