- Data center land purchases hit roughly $6 billion in the first half of 2026, up 79% year-over-year, with data centers now representing 27% of U.S. development sites — second only to apartments — per Avison Young.
- Northern Virginia site costs surpassed $8 million per acre last year per CBRE, with one Loudoun County developer reportedly offering $4.4 million per acre versus a 2025 median of $125,000, pricing homebuilders out entirely per the National Association of Home Builders.
- PJM's market monitor attributed a combined $23.1 billion increase in capacity market revenues through 2028 to data center load growth, calling it the 'primary reason' for high electricity prices across the 13-state region.
- Saline Township, Michigan officials resigned after receiving death threats over 'The Barn,' a multibillion-dollar Oracle and OpenAI data center built by Related Digital; clerk Kelly Marion said the board received messages wishing them 'a slow death.'
- Pennsylvania farmers Bobbi Thompson and Michelle Kennedy received dozens of offers for their 45-acre family farm within 20 miles of a CoreWeave data center and placed a conservation easement through the Lancaster Farmland Trust to block industrial rezoning.
- New York Gov. Kathy Hochul issued a one-year moratorium on new hyperscale data centers in July; a Sept. 1 Mizuho analysis noted as many as nine states now have pending moratoriums on new data center development.
- Boise-area developers are converting remote alfalfa farms into prime real estate, with Meta building a data center in Kuna and Micron constructing two semiconductor factories — fifth-generation Idahoan and CBRE vice president Harry Sawyer said families now face the choice of 'keep on farming? Do we sell and do something else?'
Why it matters: Data center land purchases jumped 79% in H1 2026, and with at least ten states pursuing moratoriums, the AI build-out now faces organized political resistance that Mizuho flagged as a risk to corporate capex. Homebuilders are priced out ($4.4M/acre offered in Loudoun County vs. a $125,000 median), while PJM pins $23.1 billion in added capacity costs through 2028 on data center load.