Trump invokes DPA to tackle transformer shortage

Get the Energy newsletter
Daily energy & climate — solar, EVs, oil, the policy fights and tech bets shaping the transition. Free.
- President Trump issued five presidential determinations under Section 303 of the Defense Production Act on April 20, 2026, to expand critical domestic energy capabilities, including grid equipment.
- Spencer Pederson of NEMA called the DPA action a “step in the right direction” but said its impact hinges on funding and implementation details.
- Transformer backlogs are now a year or more, roughly double the historical lead time, according to NEMA.
- Jean Su of the Center for Biological Diversity noted that FY2026 DPA funding remaining is about $323 million, and she doubts Congress will allocate more.
- White House has not confirmed the exact amount of DPA funding available for grid infrastructure.
- DPA determinations also target large‑scale energy infrastructure, gas transmission, LNG capacity, coal supply chains, and baseload power generation.
Why it matters: Domestic manufacturers stand to gain from increased federal orders, while utilities face longer lead times without funding; the limited $323 million DPA pool and uncertain congressional replenishment constrain the scale of the response, making the impact dependent on budget allocations and political pressure.