- Derril Water solar park — Britain's biggest community solar project — was ordered shut by the National Energy System Operator (Neso) weeks before the half-term heatwave to avoid a "thermal overload" from local rooftop solar pushing the transmission network's voltage beyond safety limits
- The cooperative's nearly 10,000 members are expected to lose about £2m in revenue during the shutdown, with the volunteer board warning it will "substantially impact" payments and that no compensation or insurance will cover the losses
- National Grid confirmed it curtailed generation in the local area after Neso called for a "super grid transformer" to be turned off; Neso declined to comment
- The cooperative's board said network problems in north Devon had been known since 2023, with specialist voltage-management upgrades originally due by end of 2025 now delayed until September this year
- The £42m project — funded by £20m raised from cooperative members and a £22m long-term bank loan — only began generating electricity in September 2024 under a volunteer board after original developer Ripple Energy collapsed into administration in early 2025
- Ripple Energy had marketed Derril Water as a potential "blueprint for consumer-owned solar parks around the world," promising members average energy-bill savings of at least £200 a year
Why it matters: Roughly 10,000 small investors are absorbing an estimated £2m in lost revenue because grid voltage-management upgrades in north Devon lagged behind the rapid build-out of rooftop solar — and the board's claim that operators knew of the looming constraint since 2023 points to a systemic gap between renewable deployment and transmission planning.